Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

The party platform is written every four years. a. True b. False
What is the answer of 2 2/3 - 3.5
Which lines in William Wordsworth's poem reflect the poet’s view that nature’s beauty can live on in our memories and continue to delight us even after our expe
Alexander the Great eventually established his administrative headquarters at _____. Athens Cairo Alexandria Babylon
make fractions equal by writing a number in each box (equivalent) 1/2 = / = / = / = / = /
What is the answer of 2 2/3 - 3.5
My dog Picasso was _______ after I gave him a bath. Which of the following words or phrases goes best in the blank? less dirty least dirty less dirtier least di
What is a list of numbers in a specific order
Unalienable rights what is it?
What is the approximate date for the Earth's formation? A. 4 billion BC B. 4.5 billion BC C. 4,000 BC D. 1 trillion BC E. It was there forever