Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

can someone lease tell me the answer to this question i'm abt to ask? what is 1 + 1/4?
Which two substances are reactants in the chemical reactions of cellular respiration?
someone please help me asap
PLS HELP YOU HAVE 4 MIN TO ANS
what percent of the fruit in the breakfast buffet are apples
Write a short portion of a dialogue—both sides of the conversation—in Spanish between you and your adult neighbor in complete sentences. Greet your neighbor and
A fish swims 4 feet directly above a scuba diver. The fish suddenly dives to double its depth under the surface of the ocean. The fish dives to a depth of −34 f
When drawing, intersecting lines to model a shape is called crosshatching.
Which statement best describes the chinese who immigrated to the united states in the late 1800s?.
I shall assist you with a question if you help me.